The Cambria - Window Replacement Project

Visiting Alukrom: Your Window Manufacturer for The Cambria’s Window Replacement.


As part of The Cambria’s window replacement project, TeamAB recently visited Alukrom’s leading window manufacturing facility. The visit was a valuable opportunity to see firsthand how high-quality windows are designed, engineered, and tested before making their way into you building.

Why We Visited


Replacing windows in a building like The Cambria is no small task. Beyond aesthetics, windows play a crucial role in energy efficiency, sound insulation, and your comfort.


By visiting the factory, we gained a clear understanding of the production process and quality-control measures that will directly impact our residents’ homes.


Inside the Factory


19 Views
michelle4435michelle4435
michelle4435

Leaseholders

Please find attached letter and form of mandate.




51 Views
christianwinter3christianwinter3
christianwinter3

The Cambria: Scaffolding Sequence 5 and Sequence 7

As the recladding project at the Cambria Building moves steadily forward, the scaffolding of both Sequence 5 and 7 marks a new milestone in the programme.


ree

ree

Over the next week we will be taking the window measurements in Sequence 4 to move them into manufacturing.


We met with the security company DK9 security to request an additional two security camaras installed on that scaffolded area to the front of The Cambria, these are on motion sensors and are directly linked to DK9 Security, when triggered they will come to site and stop the breach. 


We have also increased the site visits so that the security team are visible throughout the night.


31 Views
christianwinter3christianwinter3
christianwinter3

The Cambria - Regatta Quay update

Dear Residents,


We are pleased inform you that the scaffolding of Sequence 3 of The Cambria building has now been successfully completed and handed over to us. Next week we will continue with the scaffolding of Sequence 4.


On sequence one, this week we have also removed all of the adhesive from the rendered wall ready for the new render.


ree

ree

Also on sequence one, we have removed all of the concrete boards and installed 80% the new Kemwall system, we expect this to be finished next Wednesday (June 18th).


19 Views

Members

  • Glen  AttrillGlen Attrill
    Glen Attrill
  • michelle4435michelle4435
    michelle4435
  • accounts70946accounts70946
    accounts70946
  • Holly TongeHolly Tonge
    Holly Tonge
  • Camilla WhitehouseCamilla Whitehouse
    Camilla Whitehouse
bottom of page